FIELD NOTE · AGING

RFI aging and long-lead submittals

An RFI aging past its threshold, and a long-lead submittal whose procurement clock hasn't started — both read straight off Procore's own fields.

What it reads
Every RFI's own initiated date, and Procore's own record of whether it carries a known schedule impact. Every submittal's own lead-time field and its distribution date.
What it triggers
An RFI open past the configured aging threshold. A submittal whose lead time qualifies it as long-lead, still sitting in review.
What it needs from you
Nothing yet. This is an observation about elapsed time on a Procore record — not a finding against the design team, or anyone else.
Every figure, date, and party in this article is illustrative — drawn from a fictional "Project A" case built to be realistic, not a real client, GC, or project.

The exhibits

Four exhibits, each read straight from a Procore field — in the order the check assembles them.

RFI #0147

Open 31 days against Procore's own default 14-day aging threshold.

RFI #0147, "Machine room ventilation: confirm louver location and code path," against Project A. Age is measured from Procore's own initiated date.

Days open31 daysIllustrative figure

The default threshold · 14 days

The schedule impact

Procore's own record already shows a 12-day known schedule impact.

We read this field directly from Procore's own record. We never infer a schedule impact ourselves — if Procore doesn't record one, none is shown.

Known schedule impact — Procore holds it12 daysIllustrative figure

Submittal #E-14-002

23 days in review against the review SLA on this project.

Submittal #E-14-002, "Elevator shop drawings and cab finishes," distributed for review. Time in review is measured from the distribution date, not from initiation.

Days in review23 daysIllustrative figure

The review SLA on this project · 10 days

The procurement clock

A 210-day lead time that has not started — it starts at approved submittal.

The elevator equipment's quoted lead time is 30 weeks from approved submittal to delivery — this project's own quoted figure, not a typical figure for elevators generally. The clock has not started, because the submittal above has not been approved.

Quoted lead time210 daysIllustrative figure

Has not started.

The ladder stops here. It names what's aging and what's blocked — not who's responsible.

The check, in full

Two rules, two different triggers — both read straight off fields Procore already holds.

today

RFI #0147

31 days open — the default threshold is 14 days.

Submittal #E-14-002

23 days in review — the review SLA on this project is 10 days.

Elevator equipment

210 days — has not started. The clock starts at approved submittal.

One scale, one row of days: each span's length is proportional to the number of days it represents. The 210-day span is the only one that has not started — and the two that have are what is holding it.
  1. RFIs: age is measured from Procore's own initiated date. Past the configured threshold — the default is 14 days — it is raised.
  2. Severity escalates only when Procore's own record says the RFI has a known schedule impact. We read that field; we never infer it.
  3. Submittals: the gate is not elapsed time — it is Procore's own lead-time field. At or above the threshold — the default is 60 days — it counts as long-lead; time in review is measured from the distribution date.
  4. The recommendation names the ball-in-court party, and — when the project directory holds exactly one person with that name and an email — names that person. Zero matches or two matches, it names nobody. It does not guess.

What does NOT trigger it

  • A submittal with no lead time on record — excluded outright, so there's no false positive on an unknown lead time.
  • An RFI with neither an initiation date nor a due date.
  • A phone call you had that never made it into Procore.

Both rules are deterministic — the same Procore fields produce the same result every time. No model decides either one.

What this does not do

It does not decide
It flags that 31 days is past the configured threshold. It does not decide whether that's reasonable for this RFI, and it does not weigh who is at fault.
The blind spot
It reads what Procore holds. If the answer came over the phone and nobody logged it, the RFI is still open as far as this is concerned — and it will keep telling you so until somebody closes the record.
The precondition
It only ever reads Procore's own initiated date, lead-time field, and schedule-impact field — nothing here is inferred or estimated from context.
No score
There is no urgency score or risk percentage anywhere in this — two configured thresholds, read directly against two dates, is all it is.

Your call

31 days open, with the design team, and Procore's own record already shows a 12-day schedule impact.

What the recommendation does

The recommendation names the ball-in-court party — and the exact contact, if the project directory holds exactly one person with that name and an email. Zero matches or two, it names nobody. It does not guess.