FIELD NOTE · DOCUMENT CHECK

When a contract document contradicts itself

A contract document's own printed figures can fail to add up to each other — the product flags it and does not say which one is wrong.

What it reads
Every dollar figure printed on the pages of a document we read, scanned deterministically.
What triggers it
The arithmetic the printed figures assert does not hold, or a figure printed on the page is not accounted for by that arithmetic.
What it needs from you
Nothing. It fires on documents nobody has verified yet — that is the point.
Every figure, date, and party in this article is illustrative — drawn from a fictional "Project A" case built to be realistic, not a real client, GC, or project.

The exhibits

Three exhibits, in the order the check assembles them. The last one does not resolve anything — that is the point.

Page 1 — the award

Bid amount and bond, printing a total of $1,867,788.00.

Bid plus bond adds to the letter's own printed total, to the cent.

Page 1 · The award — lines that close to Total amount of this approval.
Bid Amount$1,842,000.00Illustrative figure
Bond (1.4%)$25,788.00Illustrative figure
Total amount of this approval$1,867,788.00Illustrative figureas printed

Page 2 — pending commitments

Four commitments not included in the award, printing a subtotal of $405,465.00.

The four lines add to the letter's own printed subtotal, to the cent.

Page 2 · Pending commitments — not included in the award — lines that close to Subtotal Pending Commitments.
Cab interior finish upgrade$184,500.00Illustrative figure
Hoistway pressurization coordination$96,300.00Illustrative figure
Extended maintenance term (24 months beyond base)$71,450.00Illustrative figure
Temporary use of car #2 for construction hoisting$53,215.00Illustrative figure
Subtotal Pending Commitments$405,465.00Illustrative figureas printed

The letter's own total

The award plus the pending subtotal is $2,273,253.00. The letter prints $2,741,600.00 instead.

The gap is $468,347.00, and it is not explained by anything else printed on either page.

The award, plus the pending subtotal$2,273,253.00Illustrative figure
The total printed on page 2$2,741,600.00Illustrative figure

The ladder stops here too. A mismatch is not a verdict.

The check, in full

Every sum in the letter closes to the cent except the total the letter prints for itself.

The letter's own arithmetic — three sums that close to the cent, and one that does not.
Page 1 · The award
Bid Amount$1,842,000.00Illustrative figure
Bond (1.4%)$25,788.00Illustrative figure
Total amount of this approval$1,867,788.00Illustrative figureas printed
Page 2 · Pending commitments — not included in the award
Cab interior finish upgrade$184,500.00Illustrative figure
Hoistway pressurization coordination$96,300.00Illustrative figure
Extended maintenance term (24 months beyond base)$71,450.00Illustrative figure
Temporary use of car #2 for construction hoisting$53,215.00Illustrative figure
Subtotal Pending Commitments$405,465.00Illustrative figureas printed
The award, plus the pending subtotal$2,273,253.00Illustrative figurederived
The total printed on page 2$2,741,600.00Illustrative figureas printed
$468,347.00Illustrative figure unaccounted for
Three of these sums close to the cent. The fourth is not a sum — it is a figure the letter prints and does not account for.
  1. When a document is read, every dollar figure printed on the pages we read is scanned deterministically.
  2. When the arithmetic the extracted figures assert does not hold — or a figure printed on the page is not accounted for by that arithmetic — a warning is recorded against the document.
  3. A warning raises one alert per document per kind of discrepancy.
  4. It fires on documents nobody has verified yet. That is deliberate: the alert exists to reach the rep who has not opened the file.

What does NOT trigger it

  • An informational note — those are recorded and never raise an alert.
  • A document whose figures agree.
  • Anything on a page the extraction did not read — the record says "not checked," never "consistent."

This is a deterministic check — the same inputs produce the same result every time. No model decides it.

What this does not do

It does not decide
It puts the two figures side by side. It does not tell you which one is right, and it will not.
The blind spot
It can show you that two figures do not add up. It cannot tell you which figure is the bid and which is the bond — those are words the document's author chose, and a deterministic check does not read intent. A document whose numbers happen to reconcile under the wrong labels will pass this check. That is why nothing here is a verdict.
The precondition
It only checks the pages we actually read. A figure on a page outside that range is not checked — the record says so, never "consistent."
No score
There is no confidence percentage anywhere in this, because a number shaped like evidence is not evidence.

Your call

Award, plus the pending subtotal — derived$2,273,253Illustrative figure
Printed on page 2$2,741,600Illustrative figure
Difference$468,347Illustrative figureunaccounted for — the letter does not explain it, and neither will we.

One of these is wrong. We are not going to guess which.

What the rep does next

The owner's rep asks the GC which of the letter's own totals its accounting department would stand behind, before either figure is relied on for anything downstream.